Payment of contractual fine for delay in execution of work to be treated as out of scope indemnity payment for VAT purposes

On 25 October 2017 the Belgian VAT authorities clarified in a Circular Letter that payments specifically made to repair damage caused by a delay in the execution of work have the nature of an indemnity payment. These payments thus fall outside the scope of application of VAT and should not be treated as price reductions that reduce the taxable base.

Payment of contractual fine for delay in execution of work to be treated as out of scope indemnity payment for VAT purposes

Since contractual fines for delays in the execution of work are often agreed upon when concluding agreements regarding the execution of immovable works or regarding public real estate tenders, the VAT authorities felt the urge to issue guidance in this respect.

Admittedly, it is often difficult to determine whether the payment of a contractual fine should be considered as an indemnity payment (out of scope of VAT) or as a remuneration for a service existing in the other contractual party doing or not doing something. This is especially the case when confronted with complex service agreements and management agreements. Generally speaking, a contractual fine is only to be considered as an out of scope indemnity payment if it aims to repair a damage caused by an act or omission by the other contractual party. The wording of the indemnity clauses and the correct classification of the payment remain thus extremely important for the determination of the VAT treatment.

Please do not hesitate to reach out to the Loyens & Loeff indirect tax team if you would have any questions in this respect.



Extension of the scope of the Cayman tax for E.E.A. entities

Extension of the scope of the Cayman tax for E.E.A. entities

Since 2015, entities established in the European Economic Area (E.E.A.) were only targeted by the Belgian Cayman tax if they were included in a limitative 'blacklist'.... read more
First status update of Belgian DPA after six months of GDPR

First status update of Belgian DPA after six months of GDPR

The Belgian Data Protection Authority (DPA) has issued a first status update six months after the GDPR became applicable. The statistics show a remarkable increase... read more
Loyens & Loeff congratulates SeaMade on achieving financial close for its 487 MW offshore wind farm

Loyens & Loeff congratulates SeaMade on achieving financial close for its 487 MW offshore wind farm

We advised the lenders on the EUR 1.3 billion funding for the construction of the largest offshore wind farm financed and built in Belgium. read more
Stay informed

Don't miss out. Stay up to date about our latest news and events.

Subscribe